PART IV
FLORIDA UNIFORM FEDERAL
LIEN REGISTRATION ACT (s. 713.901)
713.06 Liens of persons not in privity; proper payments.--
(1) A materialman or
laborer, either of whom is not in privity with the owner, or a
subcontractor or sub-subcontractor who complies with the provisions of
this part and is subject to the limitations thereof, has a lien on the
real property improved for any money that is owed to him or her for
labor, services, or materials furnished in accordance with his or her
contract and with the direct contract and for any unpaid finance
charges due under the lienor's contract. A materialman or laborer,
either of whom is not in privity with the owner, or a subcontractor or
sub-subcontractor who complies with the provisions of this part and is
subject to the limitations thereof, also has a lien on the owner's real
property for labor, services, or materials furnished to improve public
property if the improvement of the public property is furnished in
accordance with his or her contract and with the direct contract. The
total amount of all liens allowed under this part for furnishing labor,
services, or material covered by any certain direct contract must not
exceed the amount of the contract price fixed by the direct contract
except as provided in subsection (3). No person may have a lien under
this section except those lienors specified in it, as their
designations are defined in s. 713/Sec01.HTM713.01">713.01.
(2)(a) All lienors under
this section, except laborers, as a prerequisite to perfecting a lien
under this chapter and recording a claim of lien, must serve a notice
on the owner setting forth the lienor's name and address, a description
sufficient for identification of the real property, and the nature of
the services or materials furnished or to be furnished. A
sub-subcontractor or a materialman to a subcontractor must serve a copy
of the notice on the contractor as a prerequisite to perfecting a lien
under this chapter and recording a claim of lien. A materialman to a
sub-subcontractor must serve a copy of the notice to owner on the
contractor as a prerequisite to perfecting a lien under this chapter
and recording a claim of lien. A materialman to a sub-subcontractor
shall serve the notice to owner on the subcontractor if the materialman
knows the name and address of the subcontractor. The notice must be
served before commencing, or not later than 45 days after commencing,
to furnish his or her labor, services, or materials, but, in any event,
before the date of the owner's disbursement of the final payment after
the contractor has furnished the affidavit under subparagraph (3)(d)1.
The notice must be served regardless of the method of payments by the
owner, whether proper or improper, and does not give to the lienor
serving the notice any priority over other lienors in the same
category; and the failure to serve the notice, or to timely serve it,
is a complete defense to enforcement of a lien by any person. The
serving of the notice does not dispense with recording the claim of
lien. The notice is not a lien, cloud, or encumbrance on the real
property nor actual or constructive notice of any of them.
(b) If the owner, in his
or her notice of commencement, has designated a person in addition to
himself or herself to receive a copy of such lienor's notice, as
provided in s. 713/Sec13.HTM713.13">713.13(1)(b),
the lienor shall serve a copy of his or her notice on the person so
designated. The failure by the lienor to serve such copy, however, does
not invalidate an otherwise valid lien.
(c) The notice may be in
substantially the following form and must include the information and
the warning contained in the following form:
WARNING!
FLORIDA'S CONSTRUCTION LIEN LAW ALLOWS SOME UNPAID CONTRACTORS,
SUBCONTRACTORS, AND MATERIAL SUPPLIERS TO FILE LIENS AGAINST YOUR
PROPERTY EVEN IF YOU HAVE MADE PAYMENT IN FULL.
UNDER FLORIDA LAW, YOUR FAILURE TO MAKE SURE THAT WE ARE PAID MAY RESULT IN A LIEN AGAINST YOUR PROPERTY AND YOUR PAYING TWICE.
TO AVOID A LIEN AND PAYING TWICE, YOU MUST OBTAIN A WRITTEN RELEASE FROM US EVERY TIME YOU PAY YOUR CONTRACTOR.
NOTICE TO OWNER
To (Owner's name and address)
The undersigned hereby informs you that he or she has furnished or is furnishing services or materials as follows:
(General description of services or materials) for the improvement of the real property identified as (property description) under an order given by_______________.
Florida law prescribes the serving of this notice and restricts
your right to make payments under your contract in accordance with
Section 713/Sec06.HTM713.06">713.06, Florida Statutes.
IMPORTANT INFORMATION FOR
YOUR PROTECTION
Under Florida's laws, those
who work on your property or provide materials and are not paid have a
right to enforce their claim for payment against your property. This
claim is known as a construction lien.
If your contractor fails
to pay subcontractors or material suppliers or neglects to make other
legally required payments, the people who are owed money may look to
your property for payment, EVEN IF YOU HAVE PAID YOUR CONTRACTOR IN
FULL.
PROTECT YOURSELF:
--RECOGNIZE that this
Notice to Owner may result in a lien against your property unless all
those supplying a Notice to Owner have been paid.
--LEARN more about the Construction Lien Law, Chapter 713,
Part I, Florida Statutes, and the meaning of this notice by contacting
an attorney or the Florida Department of Business and Professional
Regulation.
(Lienor's Signature)
(Lienor's Name)
(Lienor's Address)
(d) A notice to an owner served on a lender must be in writing, must be served in accordance with s. 713/Sec18.HTM713.18">713.18,
and shall be addressed to the persons designated, if any, and to the
place and address designated in the notice of commencement. Any lender
who, after receiving a notice provided under this subsection, pays a
contractor on behalf of the owner for an improvement shall make proper
payments as provided in paragraph (3)(c) as to each such notice
received by the lender. The failure of a lender to comply with this
paragraph renders the lender liable to the owner for all damages
sustained by the owner as a result of that failure. This paragraph does
not give any person other than an owner a claim or right of action
against a lender for the failure of the lender to comply with this
paragraph. Further, this paragraph does not prohibit a lender from
disbursing construction funds at any time directly to the owner, in
which event the lender has no obligation to make proper payments under
this paragraph.
(e) A lienor, in the
absence of a recorded notice of commencement, may rely on the
information contained in the building permit application to serve the
notice prescribed in paragraphs (a), (b), and (c).
(f) If a lienor has
substantially complied with the provisions of paragraphs (a), (b), and
(c), errors or omissions do not prevent the enforcement of a claim
against a person who has not been adversely affected by such omission
or error. However, a lienor must strictly comply with the time
requirements of paragraph (a).
(3) The owner may make proper payments on the direct contract as to lienors under this section, in the following manner:
(a) If the description of the property in the notice prescribed by s. 713/Sec13.HTM713.13">713.13
is incorrect and the error adversely affects any lienor, payments made
on the direct contract shall be held improperly paid to that lienor;
but this does not apply to clerical errors when the description listed
covers the property where the improvements are.
(b) The owner may pay to
any laborers the whole or any part of the amounts that shall then be
due and payable to them respectively for labor or services performed by
them and covered by the direct contract, and shall deduct the same from
the balance due the contractor under a direct contract.
(c) When any payment becomes due to the contractor on the direct contract, except the final payment:
1. The owner shall pay or
cause to be paid, within the limitations imposed by subparagraph 2.,
the sum then due to each lienor giving notice prior to the time of the
payment. The owner may require, and, in such event, the contractor
shall furnish as a prerequisite to requiring payment to himself or
herself, an affidavit as prescribed in subparagraph (d)1., on any
payment made, or to be made, on a direct contract, but the furnishing
of the affidavit shall not relieve the owner of his or her
responsibility to pay or cause to be paid all lienors giving notice.
The owner shall be under no obligation to any lienor, except laborers,
from whom he or she has not received a notice to owner at the time of
making a payment.
2. When the payment due
is insufficient to pay all bills of lienors giving notice, the owner
shall prorate the amount then due under the direct contract among the
lienors giving notice pro rata in the manner prescribed in subsection
(4). Lienors receiving money shall execute partial releases, as
provided in s. 713/Sec20.HTM713.20">713.20(2), to the extent of the payment received.
3. If any affidavit
permitted hereunder recites any outstanding bills for labor, services,
or materials, the owner may pay the bills in full direct to the person
or firm to which they are due if the balance due on the direct contract
at the time the affidavit is given is sufficient to pay the bills and
shall deduct the amounts so paid from the balance of payment due the
contractor. This subparagraph shall not create any obligation of the
owner to pay any person who is not a lienor giving notice.
4. No person furnishing
labor or material, or both, who is required to serve a notice under
paragraph (2)(a) and who did not serve the notice and whose time for
service has expired shall be entitled to be paid by the owner because
he or she is listed in an affidavit furnished by the contractor under
subparagraph (c)1.
5. If the contract is terminated before completion, the contractor shall comply with subparagraph (d)1.
(d) When the final payment under a direct contract becomes due the contractor:
1. The contractor shall
give to the owner a final payment affidavit stating, if that be the
fact, that all lienors under his or her direct contract who have timely
served a notice to owner on the owner and the contractor have been paid
in full or, if the fact be otherwise, showing the name of each such
lienor who has not been paid in full and the amount due or to become
due each for labor, services, or materials furnished. The affidavit
must be in substantially the following form:
CONTRACTOR'S FINAL PAYMENT AFFIDAVIT
State of Florida
County of _____
Before me, the undersigned authority, personally appeared (name of affiant) , who, after being first duly sworn, deposes and says of his or her personal knowledge the following:
1. He or she is the (title of affiant) , of (name of contractor's business) , which does business in the State of Florida, hereinafter referred to as the "Contractor."
2. Contractor, pursuant to a contract with (name of owner) ,
hereinafter referred to as the "Owner," has furnished or caused to be
furnished labor, materials, and services for the construction of
certain improvements to real property as more particularly set forth in
said contract.
3. This affidavit is executed by the Contractor in accordance with section 713/Sec06.HTM713.06">713.06 of the Florida Statutes for the purposes of obtaining final payment from the Owner in the amount of $_____.
4. All work to be
performed under the contract has been fully completed, and all lienors
under the direct contract have been paid in full, except the following
listed lienors:
NAME OF LIENOR____________________AMOUNT DUE
Signed, sealed, and delivered this _____ day of _____, _____,
By (name of affiant)
(title of affiant)
(name of contractor's business)
Sworn to and subscribed before me this _____ day of _____ by (name of affiant) , who is personally known to me or produced _____ as identification, and did take an oath.
(name of notary public)
Notary Public
My Commission Expires:
(date of expiration of commission)
The contractor shall have no lien or right of action against
the owner for labor, services, or materials furnished under the direct
contract while in default for not giving the owner the affidavit;
however, the negligent inclusion or omission of any information in the
affidavit which has not prejudiced the owner does not constitute a
default that operates to defeat an otherwise valid lien. The contractor
shall execute the affidavit and deliver it to the owner at least 5 days
before instituting an action as a prerequisite to the institution of
any action to enforce his or her lien under this chapter, even if the
final payment has not become due because the contract is terminated for
a reason other than completion and regardless of whether the contractor
has any lienors working under him or her or not.
2. If the contractor's
affidavit required in this subsection recites any outstanding bills for
labor, services, or materials, the owner may, after giving the
contractor at least 10 days' written notice, pay such bills in full
direct to the person or firm to which they are due, if the balance due
on a direct contract at the time the affidavit is given is sufficient
to pay them and lienors giving notice, and shall deduct the amounts so
paid from the balance due the contractor. Lienors listed in said
affidavit not giving notice, whose 45-day notice time has not expired,
shall be paid in full or pro rata, as appropriate, from any balance
then remaining due the contractor; but no lienor whose notice time has
expired shall be paid by the owner or by any other person except the
person with whom that lienor has a contract.
3. If the balance due is
not sufficient to pay in full all lienors listed in the affidavit and
entitled to payment from the owner under this part and other lienors
giving notice, the owner shall pay no money to anyone until such time
as the contractor has furnished him or her with the difference;
however, if the contractor fails to furnish the difference within 10
days from delivery of the affidavit or notice from the owner to the
contractor to furnish the affidavit, the owner shall determine the
amount due each lienor and shall disburse to them the amounts due from
him or her on a direct contract in accordance with the procedure
established by subsection (4).
4. The owner shall have
the right to rely on the contractor's affidavit given under this
paragraph in making the final payment, unless there are lienors giving
notice who are not listed in the affidavit. If there are lienors giving
notice who are not so listed, the owner may pay such lienors and any
persons listed in the affidavit that are entitled to be paid by the
owner under subparagraph 2. and shall thereupon be discharged of any
further responsibility under the direct contract, except for any
balance that may be due to the contractor.
5. The owner shall
retain the final payment due under the direct contract that shall not
be disbursed until the contractor's affidavit under subparagraph 1. has
been furnished to the owner.
6. When final payment
has become due to the contractor and the owner fails to withhold as
required by subparagraph 5., the property improved shall be subject to
the full amount of all valid liens of which the owner has notice at the
time the contractor furnishes his or her affidavit.
(e) If the improvement
is abandoned before completion, the owner shall determine the amount
due each lienor giving notice and shall pay the same in full or prorate
in the same manner as provided in subsection (4).
(f) No contractor shall
have any right to require the owner to pay any money to him or her
under a direct contract if such money cannot be properly paid by the
owner to the contractor in accordance with this section.
(g) Except with written
consent of the contractor, before paying any money directly to any
lienor except the contractor or any laborer, the owner shall give the
contractor at least 10 days' written notice of his or her intention to
do so, and the amount he or she proposes to pay each lienor.
(h) When the owner has
properly retained all sums required in this section to be retained but
has otherwise made improper payments, the owner's real property shall
be liable to all laborers, subcontractors, sub-subcontractors, and
materialmen complying with this chapter only to the extent of the
retentions and the improper payments, notwithstanding the other
provisions of this subsection. Any money paid by the owner on a direct
contract, the payment of which is proved to have caused no detriment to
any certain lienor, shall be held properly paid as to the lienor, and
if any of the money shall be held not properly paid as to any other
lienors, the entire benefit of its being held not properly paid as to
them shall go to the lienors.
(4)(a) In determining
the amounts for which liens between lienors claiming under a direct
contract shall be paid by the owner or allowed by the court within the
total amount fixed by the direct contract and under the provisions of
this section, the owner or court shall pay or allow such liens in the
following order:
1. Liens of all laborers.
2. Liens of all persons other than the contractor.
3. Lien of the contractor.
(b) Should the total
amount for which liens under such direct contract may be allowed be
less than the total amount of liens under such contract in all classes
above mentioned, all liens in a class shall be allowed for their full
amounts before any liens shall be allowed to any subsequent class.
Should the amount applicable to the liens of any single class be
insufficient to permit all liens within that class to be allowed for
their full amounts, each lien shall be allowed for its pro rata share
of the total amount applicable to liens of that class; but if the same
labor, services, or materials shall be covered by liens of more than
one class, such labor, services, or materials shall be allowed only in
the earliest class by which they shall be covered; and also if the same
labor, services, or materials shall be covered by liens of two or more
lienors of the same class, such labor, services, or materials shall be
allowed only in the lien of the lienor farthest removed from the
contractor. This section shall not be construed to affect the priority
of liens derived under separate direct contracts.
History.--s.
1, ch. 63-135; ss. 4, 5, ch. 65-456; s. 35, ch. 67-254; s. 1, ch.
75-227; s. 5, ch. 77-353; s. 4, ch. 80-97; s. 3, ch. 87-74; s. 4, ch.
90-109; s. 1, ch. 93-99; s. 318, ch. 94-119; s. 229, ch. 94-218; s. 2,
ch. 96-383; s. 1764, ch. 97-102; s. 2, ch. 97-219; s. 3, ch. 98-135; s.
3, ch. 99-386; ss. 2, 3, ch. 2003-177.
Note.--Former s. 84.061.